Case Study // 03
Fifth Third Bank
— Fremont, OH
Location
Fremont, Ohio
Scope
Milling, 5E1 Asphalt & ADA Upgrades
Delivered a complete parking facility rejuvenation featuring 1.5" precision milling, SS-1 bonding agent, 5E1 asphalt topcoat, catch basin masonry rebuilding, and ADA-compliant concrete pads with under 2% slope in all directions.

1.5 Inches
Milling Depth
< 2.0%
ADA Pad Gradient
5E1 Mix
Heavy Wear Asphalt
100%
On-Budget Delivery
Project
Specifications
This comprehensive capital project was designed to rejuvenate the active commercial parking facility at Fifth Third Bank in Fremont, OH. The scope included full procurement of materials, heavy machinery, and specialized paving crews.
Key operational priorities included tight expenditure control, maintaining safe and uninterrupted customer access to the bank and drive-thru lanes, and adhering to phased construction mapping coordinated with the branch manager.
Operational Log // Material Verification
REF: FTB-FRM-OH
01
1.5" Milling & Sweeping
Milled existing parking surface to a 1.5" depth, followed by power sweeping to clear fine debris before off-site recycling.
02
Full-Depth Excavation & ADA Pads
Excavated compromised base zones and prepared concrete pad subgrades calibrated to under 2% slope in all directions for ADA compliance.
03
Catch Basin Apron Rebuild
Rehabilitated catch basin frames and covers, replaced deteriorated manhole blocks, and reset structures to precise flush elevations.
04
SS-1 Tack & 5E1 Wearing Course
Sprayed uniform SS-1 tack coat and installed 1.5" 5E1 asphalt topcoat, compacted for exceptional surface density and durability.
05
Reinforced Concrete & Striping
Poured reinforced concrete with tooled joints and saw cuts, followed by full ADA stall striping, directional arrows, and stall numbering.
Diagnostic Portfolio
Visual Phase Proof
Step-by-step visual documentation from heavy 1.5" asphalt milling and subbase preparation to 5E1 paving and ADA concrete finishing in Fremont, OH.

1.5" Milling & Sweeping
Cold-milled entire parking field to uniform 1.5" depth; power-swept debris.

Catch Basin Masonry
Rebuilt deteriorated manhole blocks and reset casting frames to grade.

SS-1 Tack & 5E1 Paving
Applied SS-1 bonding agent and 1.5" compacted 5E1 wearing course.

ADA Pads & Striping
Poured <2% slope concrete pads, installed ADA signage and stall striping.
Operational Flow
Phased Execution Plan
Precision phasing allowed bank operations and drive-thru teller lanes to remain fully active while heavy cold milling and paving machinery completed full-depth restorations.
01
Preparation & 1.5" Milling
The entire parking lot underwent comprehensive cold milling to a precise depth of 1.5 inches. High-capacity power sweepers immediately cleared all aggregate dust and milled material, which was hauled off-site to a licensed recycling facility.
02
Asphalt & Concrete Removal / Subgrade Prep
Excavated failing asphalt down to the stone base in targeted stress areas for full-depth base stabilization. Subgrades for designated ADA parking pads were graded to ensure strict compliance with federal ADA guidelines requiring less than a 2% slope in all directions.
03
Drainage & Catch Basin Infrastructure Rehab
Preserved and cleaned heavy iron casting frames and storm grates. Rebuilt crumbling internal brick and manhole block courses, mortared all joints watertight, and reset castings to finished pavement elevation with reinforced concrete collars.
04
Reinforced Concrete Pouring & Finishing
Poured commercial-grade concrete reinforced with welded wire mesh. Formed tooled expansion joints and early-entry saw cuts in accordance with engineering standards to prevent cracking and guarantee long-term freeze-thaw durability.
05
SS-1 Tack Coating, 5E1 Paving & Precision Striping
Applied SS-1 emulsion bonding tack across the milled surface, followed by 1.5 inches of high-density 5E1 asphalt mix compacted with multi-ton tandem vibratory rollers. Applied crisp traffic-rated paint for ADA stalls, handicap symbols, and parking lines.
Commercial Portfolio
Featured Case Studies
Documented Industrial Proof

Monroe, MI
Walgreen’s
Asphalt & $50k Saved

Troy, MI
Bright Horizons
Lot Expansion

Fremont, OH
Fifth Third Bank
Milling & 5E1 Paving

Dearborn, MI
Chase Bank
ADA Upgrades

Clinton Township, MI
Morelli
Commercial Concrete & Asphalt Replacement
FIELD OFFICE READY
HAVE A COMMERCIAL PROPERTY IN NEED OF RECONSTRUCTION?
Contact D&J Contracting Inc. for certified ADA upgrades, parking lot paving, and high-durability concrete installations. Professional bidding for facility directors and property managers.